Israel's Electricity Authority caps new data center connection capacity at 200MW, with per-megawatt guarantees

The reported rules follow a queue of about 27GW of projects and require NIS 2 million ($643,300) in guarantees per megawatt requested.

At a glance

20-second brief
  • Israel's Electricity Authority has capped new data center connection capacity at 200MW, Data Center Dynamics reported on 19 October, citing Calcalistech.

  • Developers will have to provide guarantees of NIS 2 million ($643,300) for every megawatt of connection capacity they request.

  • At the stated rate, a project requesting the full 200MW would need guarantees of about $129 million.

Israel's Electricity Authority has capped new data center connection capacity at 200MW, Data Center Dynamics reported on 19 October, citing Calcalistech.

Developers will have to provide guarantees of NIS 2 million ($643,300) for every megawatt of connection capacity they request. They must also install backup mechanisms that allow data centers to be disconnected from the grid during periods of high demand.

At the stated rate, a project requesting the full 200MW would need guarantees of about $129 million.

NOGA, the national system operator, said it had about 27GW of projects seeking a grid connection. In July it issued a temporary order freezing responses to data center requests of 8MW or more. That freeze is expected to run until early December while the Electricity Authority, the Ministry of Energy and NOGA complete a joint review of how to divide power between data centers and the rest of the economy.

Alongside the cap, the authority said it would allocate an additional 1GW to large data centers, lifting the sector's contracted capacity above 3GW. If realized, that would account for around 20% of the country's electricity consumption in 2030.

Officials traced the surge in connection requests to the National Cyber Defense Bill, passed by the Knesset in February, which designated data centers as national infrastructure in order to remove planning and construction constraints. They described the cap and guarantee requirement as the policy response.

The report does not specify whether the 200MW cap applies per project, per site, or per developer, which determines whether a sponsor can stack multiple campuses inside the cap.

The rules are not final. A full decision is slated for publication in the coming days, following a three-week public consultation.

Israel's new 200MW data center cap against the grid queue
Capacity in megawatts
Cap per Data cenProjects
DATA CENTER DYNAMICS, CITING CALCALISTECH · OCT
Continue your research

Save this analysis and keep the funds you follow together in My Desk.

Sign in to save articles or follow funds.
Sources & further reading
Data Center Dynamics
More from Private Infrastructure Daily
Digital Infra

Alcoa to sell Massena smelter site to data center developer for up to $315m

Alcoa expects $50m to $65m at closing, with up to $250m more as the buyer's capacity is approved and commissioned.
Digital Infra

Microsoft exits Nscale's Loughton data center as grid power slips to 2030s

Nscale says it remains committed to Loughton and is exploring alternative power sources; the site had targeted late-2026 completion.
The Wrap

Microsoft-NiSource power deal makes data center customer fund its own generation

The 20-year contract, closed Oct. 19, adds roughly 1.1GW to NiSource's portfolio from 2028 and covers a northern Indiana data center.
Elsewhere in the networkAll titles →
Every weekday · 6:30 a.m. ET

The Morning Brief

The latest from Private Infrastructure Daily, in your inbox every weekday. Free.