Israel's Electricity Authority

In network coverage since October 19, 2026 · 1 story
Network coverage
digital

Israel's Electricity Authority caps new data center connection capacity at 200MW, with per-megawatt guarantees

The reported rules follow a queue of about 27GW of projects and require NIS 2 million ($643,300) in guarantees per megawatt requested.