GreenSquare opens SYD1 phase one with Sharon AI as anchor tenant

The eight-month retrofit reused a 1995 IBM data center; a planned 80MW addition would take the Sydney campus to 110MW.

At a glance

20-second brief
  • GreenSquare said this week that the first phase of its SYD1 data center campus in Western Sydney is operational, with Australian AI cloud provider Sharon AI as anchor tenant.

  • Sharon AI is deploying approximately 8,200 Nvidia Blackwell Ultra GPUs at the facility.

  • GreenSquare plans a further 80MW development on the campus, which it says would take the site to 110MW.

GreenSquare said this week that the first phase of its SYD1 data center campus in Western Sydney is operational, with Australian AI cloud provider Sharon AI as anchor tenant.

Sharon AI is deploying approximately 8,200 Nvidia Blackwell Ultra GPUs at the facility. The Nasdaq-listed company takes capacity from Equinix in Sydney and NextDC in Melbourne and is partnering with CDC. It says it has 212MW online or in development, with some 64,000 Nvidia GPUs due to be deployed by mid-2027.

The phase reuses an IBM data center that opened at 3 Brookhollow Avenue in 1995. GreenSquare delivered it in eight months after main construction began in February 2026, working with Erilyan and Fredon. It kept the existing slab and moved the data halls to the ground floor so higher-density compute needed no structural reinforcement; GreenSquare says that lifted IT capacity within the original building footprint by 275%. The original cooling towers were replaced with a closed-loop system that runs without evaporative cooling for about 96% of the year, and rainwater harvesting is expected to offset roughly 10% of annual cooling water demand.

GreenSquare plans a further 80MW development on the campus, which it says would take the site to 110MW. Those figures imply roughly 30MW in the phase now live, though the announcement does not break out current capacity. It also does not give the cost of the retrofit or of the expansion.

GreenSquareDC launched in October 2022 and was acquired by Partners Group in March 2025. The Sydney phase reaches service with a customer already named; this publication noted in September that New Era's phase one still had none.

Its $365m of SPV debt came at 9.95%, as this publication reported, against 6.78% on Lambda's $1bn facility, a 317 basis point gap between two GPU-backed borrowers. GreenSquare's announcement gives no start or delivery date for the 80MW addition.

Continue your research

Save this analysis and keep the funds you follow together in My Desk.

Sign in to save articles or follow funds.
Sources & further reading
Data Center Dynamics · Private Infrastructure Daily archive
More from Private Infrastructure Daily
Digital Infra

Alcoa to sell Massena smelter site to data center developer for up to $315m

Alcoa expects $50m to $65m at closing, with up to $250m more as the buyer's capacity is approved and commissioned.
Digital Infra

Microsoft exits Nscale's Loughton data center as grid power slips to 2030s

Nscale says it remains committed to Loughton and is exploring alternative power sources; the site had targeted late-2026 completion.
The Wrap

Microsoft-NiSource power deal makes data center customer fund its own generation

The 20-year contract, closed Oct. 19, adds roughly 1.1GW to NiSource's portfolio from 2028 and covers a northern Indiana data center.
Elsewhere in the networkAll titles →
Every weekday · 6:30 a.m. ET

The Morning Brief

The latest from Private Infrastructure Daily, in your inbox every weekday. Free.