Crusoe files for a $4.8bn data center campus in Jayton, Texas
The two buildings are slated to go live in 2029, and the filings name no tenant, landowner or power source.
Crusoe has filed for two data center buildings in Jayton, in Kent County, Texas, and the two filings with the Texas Department of Licensing and Regulation put $4.8 billion of total investment in the site on the state's record without naming a tenant, a landowner or a power source. Each building is planned at 759,260 square feet, on land the filings locate along County Road 233 and P2390, with construction scheduled to begin at the end of January 2027 and the buildings expected to go live in May and July 2029.
The filings list both Jayton buildings as "spur buildings" of Project Hyper, the Childress development Crusoe filed in September, and that designation, more than the square footage, sizes the story. Project Hyper is three data center buildings at 525 B CO RD 23, each spanning 806,360 square feet, with roughly $2.4 billion expected in each; two are already under construction, the third is expected to follow this month, and all three target completion in the first half of 2028. Jayton's total across two buildings works out to about the same per-building ticket, and the two sites together represent $12 billion of Project Hyper investment.
Geography reinforces the satellite reading. Jayton sits south of Childress and north of Abilene, where Crusoe is also developing, placing the new filing inside a West Texas corridor of Crusoe sites rather than at a fresh frontier; whether the three locations share power, labor or procurement is not described.
Childress is where Crusoe's Texas thesis is most legible. The company announced in July 2026 that it was working with Lancium on a 1.4GW data center campus there, a grid-connected project spanning 270 acres owned by Lancium, which will also develop and manage the site's energy infrastructure. The site was said to include behind-the-meter solar and energy storage, the data centers will use a closed-loop cooling system to cut water use, and previous reports suggest Meta is set to lease capacity from Crusoe at Childress. The campus sits adjacent to Iren's site in Childress, which is leased to Microsoft.
Everywhere else in Crusoe's disclosed Texas footprint the tenant side is clear too: the campus under development for Google in Armstrong County, the Abilene site being used by OpenAI, further Abilene capacity set to be leased to Microsoft. Jayton is the site on that list carrying a price and no name.
The spur designation is doing the work
The absence of a named tenant, landowner or power source in the Kent County filings leaves the spur designation as the only thing pointing at where the load might come from, and the report reads it as making Jayton a likely satellite of Childress rather than an independent campus. If that holds, Jayton is expansion capacity attached to a relationship that already exists and the offtake question belongs at Childress, but the label only invites that reading without proving it.
How it resolves matters for the price. Digital infrastructure has split into two markets: assets anchored by a named hyperscaler or AI lab are underwritten close to utility risk, while everything else carries merchant risk until a lease exists. A $4.8 billion construction filing with no tenant on it lands, on its face, in the second bucket, and the spur label is the argument for the first. A label is weaker evidence than a signed contract, which is the gap between Jayton and the rest of Crusoe's Texas book, where the anchor is named or reported in every case.
Power is the second missing name
Childress pairs its load with a 1.4GW grid-connected campus, 270 acres owned by Lancium, and an energy manager that also develops and manages the site's generation, including behind-the-meter solar and storage. Grid access now behaves as much like a customer class as a queue position, set by who brings the load and the budget line behind it. The Jayton filings, as reported, describe no interconnection, no generation and no energy partner, which for an asset a reader would underwrite on contracted capacity and delivered megawatts is the disclosure that is still missing.
The delivery dates also line up: Childress completes in the first half of 2028, while Jayton's two buildings go live in May and July 2029, roughly a year behind. Filing a second site on that spacing reads as a pipeline being permitted ahead of demand rather than a single project, and it means Jayton will not be testing the leasing market this year or next.
The third Childress building is expected to start this month, and Project Hyper's offtake, whichever way Jayton resolves, will surface at Childress first, where the anchor relationships, the Lancium energy arrangement and the 2028 completion dates all sit. Construction in Kent County is scheduled to begin at the end of January 2027 and the buildings are not due to go live until May and July 2029, which leaves a long stretch in which a tenant, a landowner and an energy partner could still reach the record.