atNorth tops out Espoo data center expansion under €100m Skanska contract

The five-story FIN02 addition began construction in April 2026 and is scheduled for completion in Q3 2027.

At a glance

20-second brief
  • atNorth has topped out a five-story expansion at its FIN02 data center in Espoo, Finland, under a €100 million ($112 million) Skanska contract awarded in May 2026.

  • The new building totals 11,200 sqm (120,555 sq ft), with construction underway since April 2026 and completion due in Q3 2027.

  • At full build-out the Espoo site will total 40MW across 20,050 sqm.

atNorth has topped out a five-story expansion at its FIN02 data center in Espoo, Finland, under a €100 million ($112 million) Skanska contract awarded in May 2026. The company announced the milestone this week on LinkedIn, describing the project as "another step in atNorth's continued investment in Finland" and a response to demand for reliable, high-performance digital infrastructure.

The new building totals 11,200 sqm (120,555 sq ft), with construction underway since April 2026 and completion due in Q3 2027. Divided by floor area, the contract works out to roughly €8,900 per sqm — a build-cost marker to set against the structural lead times this publication has tracked.

At full build-out the Espoo site will total 40MW across 20,050 sqm. The original 15MW facility was announced in 2023 and launched in October 2025.

Ownership has changed since that first phase was announced: Equinix and CPP acquired atNorth earlier this year, after Partners Group bought the company in 2021. atNorth operates seven data centers across Sweden, Iceland and Finland, with further sites under development in Finland, Denmark, Sweden and Norway.

atNorth's Finnish sites by capacity, MW
Espoo's full build-out sits well below the two projects still to come
FIN02 EsFIN04 KoFIN05 Sa
COMPANY FIGURES VIA DATA CENTER DYNAMICS · AUG 2026
Divided by floor area, the contract works out to roughly €8,900 per sqm — a build-cost marker to set against the structural lead times this publication has tracked.
Continue your research

Save this analysis and keep the funds you follow together in My Desk.

Sign in to save articles or follow funds.
Sources & further reading
Data Center Dynamics
More from Private Infrastructure Daily
Digital Infra

Vantage signs 1GW solid-state transformer supply deal with Heron Power

Heron says its Heron Link units target more than 98.5% efficiency converting medium-voltage grid power to 800VDC for AI racks.
Digital Infra

NorthC starts 4.5MW data center in Meyrin, outside Geneva

The 5,400 sqm build is expected to be complete by the second quarter of 2028, with 1.5MW capacity increments and waterless cooling.
Capital

Ara Partners launches Ara Energy Fund I with $2.5bn in assets

The Oct. 21 record names the fund and size but does not state a strategy, sector split or named investors.
Elsewhere in the networkAll titles →
Every weekday · 6:30 a.m. ET

The Morning Brief

The latest from Private Infrastructure Daily, in your inbox every weekday. Free.