AEP to buy up to 1.6 GW Mainspring units, plans $4B Cheyenne fuel cells

The eight-year Mainspring agreement carries a stated ceiling of up to $4 billion; the 702 MW Cheyenne project pairs Bloom Energy fuel cells with a 20-year Google PPA.

At a glance

25-second brief
  • American Electric Power has agreed to buy up to 1.6 gigawatts of Mainspring linear generators over eight years under a contract with a stated ceiling of up to $4 billion.

  • AEP also plans a 702-megawatt Cheyenne fuel cell project using Bloom Energy fuel cells and backed by a 20-year Google power purchase agreement.

  • The two initiatives carry separate $4 billion figures: the Mainspring agreement is a purchase ceiling, while the Cheyenne project is a planned $4 billion cost.

American Electric Power has agreed to buy up to 1.6 gigawatts of Mainspring linear generators over eight years under a contract with a stated ceiling of up to $4 billion.

AEP also plans a 702-megawatt Cheyenne fuel cell project using Bloom Energy fuel cells and backed by a 20-year Google power purchase agreement.

The two initiatives carry separate $4 billion figures: the Mainspring agreement is a purchase ceiling, while the Cheyenne project is a planned $4 billion cost.

Continue your research

Save this analysis and keep the funds you follow together in My Desk.

Sign in to save articles or follow funds.
Sources & further reading
Private Infrastructure Daily data pack
More from Private Infrastructure Daily
The Wrap

FERC approves Duke Energy Carolinas large-load rules requiring 75% payment for 15 years

New or transferred large loads must pay a committed revenue contribution equal to 75% of the megawatt value in the load schedule for 15 years.
The Wrap

JE Dunn-Alberici JV starts construction on Saronic's $3.2B Texas shipyard

Saronic's initial 835-acre Port Alpha site can expand to nearly 4,400 acres.
The Wrap

Oregon pauses data center permits until July 2027; Taylor approves 1GW gas campus

The Oregon pause covers air-quality permits and municipal wastewater applications; the PowerHouse-Big Watt campus would pair a 750MW on-site plant with a 500MW first phase.