Oregon pauses data center permits until July 2027; Taylor approves 1GW gas campus

The Oregon pause covers air-quality permits and municipal wastewater applications; the PowerHouse-Big Watt campus would pair a 750MW on-site plant with a 500MW first phase.

At a glance

20-second brief
  • Oregon Governor Tina Kotek directed the Department of Environmental Quality to pause issuing air quality permits and municipal wastewater applications for data centers until July 2027.

  • Taylor, Texas, approved a 1GW gas-backed campus proposed by PowerHouse and Big Watt.

  • The Oregon directive follows a September order that halted state land sales for data centers, narrowing state-level permitting and land pathways for new projects through at least mid-2027.

Oregon Governor Tina Kotek directed the Department of Environmental Quality to pause issuing air quality permits and municipal wastewater applications for data centers until July 2027.

Taylor, Texas, approved a 1GW gas-backed campus proposed by PowerHouse and Big Watt. The project would occupy a 664-acre Williamson County site and pair a 750MW on-site power plant with a first phase targeting 500MW. First power is targeted for the first half of 2028.

The Oregon directive follows a September order that halted state land sales for data centers, narrowing state-level permitting and land pathways for new projects through at least mid-2027.

Taylor, Texas: 1GW campus, 750MW on-site gas, 500MW first phase
PowerHouse and Big Watt project, Williamson County
Campus tOn-site First ph
COMPANY PROJECT DISCLOSURE · OCT 2026
Continue your research

Save this analysis and keep the funds you follow together in My Desk.

Sign in to save articles or follow funds.
Sources & further reading
Private Infrastructure Daily data pack
More from Private Infrastructure Daily
The Wrap

JE Dunn-Alberici JV starts construction on Saronic's $3.2B Texas shipyard

Saronic's initial 835-acre Port Alpha site can expand to nearly 4,400 acres.
The Wrap

CVC's Naturgy stake sale and Greenvolt battery debt reported without key terms

Renewables Now reported CVC's sale of its entire 13.8% Naturgy stake and Greenvolt's UniCredit debt for a 400 MW Polish battery portfolio; neither report gives a price, facility size or tenor.
Capital

Ares and Astatine file SEC registrations for three pooled infrastructure vehicles

The vehicles list an undisclosed offering amount and $0 sold to date; SWI raised €800 million for data-center buildouts.
Elsewhere in the networkAll titles →
Every weekday · 6:30 a.m. ET

The Morning Brief

The latest from Private Infrastructure Daily, in your inbox every weekday. Free.