FERC approves Duke Energy Carolinas large-load rules requiring 75% payment for 15 years
New or transferred large loads must pay a committed revenue contribution equal to 75% of the megawatt value in the load schedule for 15 years.
At a glance
FERC has approved Duke Energy Carolinas large-load rules that require new or transferred large loads to commit to paying 75% of their scheduled megawatt value for 15 years.
The committed revenue contribution is calculated from the load's megawatt value in the load schedule.
FERC has approved Duke Energy Carolinas large-load rules that require new or transferred large loads to commit to paying 75% of their scheduled megawatt value for 15 years.
The committed revenue contribution is calculated from the load's megawatt value in the load schedule.