SoftBank asks PJM to study 10-GW Ohio data center complex under state agreement

The filing pairs 9.6 GW of added load with 10.2 GW of SB Energy gas-fired generation through 2032 and three new AEP Ohio 765-kV lines.

At a glance

20-second brief
  • SoftBank has asked PJM to study a 10-gigawatt data center complex in Ohio under a state agreement approach.

  • The filing shows 9.6 GW of added load, 10.2 GW of SB Energy gas-fired generation through 2032, and three new AEP Ohio 765-kilovolt lines.

  • The study would run through the state agreement approach rather than a standard interconnection queue request, evaluating load and generation as one package.

SoftBank has asked PJM to study a 10-gigawatt data center complex in Ohio under a state agreement approach.

The filing shows 9.6 GW of added load, 10.2 GW of SB Energy gas-fired generation through 2032, and three new AEP Ohio 765-kilovolt lines.

The study would run through the state agreement approach rather than a standard interconnection queue request, evaluating load and generation as one package. The generation is sized above the load it would serve, and the three 765-kV lines would be new construction.

Oracle and Google each moved data center power projects forward this week with generation already attached. Oracle asked FERC to expedite a 17.8-mile gas pipeline in New Mexico, the Green Chile line, to carry about 400 million cubic feet a day to on-site fuel cells for Project Jupiter. Google signed a 20-year power purchase agreement with American Electric Power for a 702-megawatt Wyoming fuel cell plant; AEP owns 92% of Cheyenne Fuel Cell and funds advised by Basalt Infrastructure Partners own 8%. The power price was not disclosed.

PowerHouse and Big Watt won approval in Taylor, Texas for a 1-gigawatt gas-backed campus on 664 acres in Williamson County. The campus pairs a 750-megawatt on-site plant with a 500-megawatt first phase and first power targeted for the first half of 2028. SoftBank's Ohio request is roughly ten times that load.

Continue your research

Save this analysis and keep the funds you follow together in My Desk.

Sign in to save articles or follow funds.
Sources & further reading
our tracking (deal log) · Data Center Dynamics
More from Private Infrastructure Daily
The Wrap

FERC approves Duke Energy Carolinas large-load rules requiring 75% payment for 15 years

New or transferred large loads must pay a committed revenue contribution equal to 75% of the megawatt value in the load schedule for 15 years.
The Wrap

JE Dunn-Alberici JV starts construction on Saronic's $3.2B Texas shipyard

Saronic's initial 835-acre Port Alpha site can expand to nearly 4,400 acres.
The Wrap

Oregon pauses data center permits until July 2027; Taylor approves 1GW gas campus

The Oregon pause covers air-quality permits and municipal wastewater applications; the PowerHouse-Big Watt campus would pair a 750MW on-site plant with a 500MW first phase.
Elsewhere in the networkAll titles →
Every weekday · 6:30 a.m. ET

The Morning Brief

The latest from Private Infrastructure Daily, in your inbox every weekday. Free.