Pure Data Centres completes final Brent Cross transformer ahead of energization

The third 75MVA Hitachi Energy unit brings the LON01 substation to 150MVA; the second building is slated for completion in Q2 2029.

At a glance

25-second brief
  • Pure Data Centres has completed installation of the third and final transformer at its LON01 campus in Brent Cross, London, bringing the substation's total capacity to 150MVA.

  • Hitachi Energy supplied the 75MVA transformers, which Pure says will support power supply to the campus's B1 and B2 buildings, with ductwork already in place for the B2 connection.

  • PID reported in September that the Brent Cross shell was announced without a named tenant.

Pure Data Centres has completed installation of the third and final transformer at its LON01 campus in Brent Cross, London, bringing the substation's total capacity to 150MVA. Energization of the 90MW campus is expected later this month, according to Data Center Dynamics.

Hitachi Energy supplied the 75MVA transformers, which Pure says will support power supply to the campus's B1 and B2 buildings, with ductwork already in place for the B2 connection. Because restricted space around the live substation ruled out a conventional 500-ton crane, the project team built a specialist gantry system with 1,000 tons of lifting capacity to move the unit into position.

PID reported in September that the Brent Cross shell was announced without a named tenant.

Work on the second building began last month, with completion slated for Q2 2029. LON01 will use closed-loop liquid cooling for high-density AI inference and cloud workloads, and B2 is to carry a living wall that Pure describes as one of the world's largest, with more than 750,000 plants.

Continue your research

Save this analysis and keep the funds you follow together in My Desk.

Sign in to save articles or follow funds.
Sources & further reading
Data Center Dynamics
More from Private Infrastructure Daily
Digital Infra

CapitaLand Investment unveils 53MW Chennai data center for end-2026 completion

The Ambattur facility, jointly held by CapitaLand India Trust and CapitaLand India Data Centre Fund, will offer 34MW of IT power in 13 data halls.
Digital Infra

Langenhorn council advances Uniq Land's 150MW data center plan

The August 26 vote opens planning studies, but a 300MW expansion and wind-powered supply depend on regional grid upgrades.
The Wrap

AEP to buy up to 1.6 GW Mainspring units, plans $4B Cheyenne fuel cells

The eight-year Mainspring agreement carries a stated ceiling of up to $4 billion; the 702 MW Cheyenne project pairs Bloom Energy fuel cells with a 20-year Google PPA.
Elsewhere in the networkAll titles →
Every weekday · 6:30 a.m. ET

The Morning Brief

The latest from Private Infrastructure Daily, in your inbox every weekday. Free.