Nscale's Glomfjord data center six months behind schedule as IPO nears

Only 6.4MW of the Norwegian site's planned 30MW is operational, according to a Bloomberg report relayed by Data Center Dynamics.

At a glance

20-second brief
  • Nscale's Glomfjord data center in Norway is about six months behind schedule, with 6.4MW of a planned 30MW operational, according to a Bloomberg report relayed by Data Center Dynamics.

  • Nscale is preparing an initial public offering, with reports suggesting it could seek a valuation of up to $35 billion.

  • Nscale reports $103 billion in total contracted value, largely contracts with Anthropic and Microsoft.

Nscale's Glomfjord data center in Norway is about six months behind schedule, with 6.4MW of a planned 30MW operational, according to a Bloomberg report relayed by Data Center Dynamics.

The report cites people close to the project and public records for the setbacks: construction delays, local regulations, cooling-system leaks and a transformer fire. Bloomberg also reports that Nscale towed in the Kalmar floating hotel to house construction workers nearby, a step aimed at speeding construction.

Nscale is preparing an initial public offering, with reports suggesting it could seek a valuation of up to $35 billion. Its prospectus, published in September, lists five active data centers totaling 55MW, with 12 more in development, and includes construction delays, construction site accidents and permit delays among its risk factors.

Nscale reports $103 billion in total contracted value, largely contracts with Anthropic and Microsoft. Revenue for the six months to the end of June 2026 came to $140.6 million. The company says that figure is up 1,252 percent year over year. Losses were $1.02 billion, compared with $368.9 million in the same period of 2025.

Nscale's half-year loss dwarfed its revenue
Six months to end of June 2026, compared with the same period a year earlier
H1 2026 net loss$1K
H1 2025 net loss$368.9M
H1 2026 revenue$140.6M
COMPANY IPO PROSPECTUS VIA DATA CENTER DYNAMICS
Continue your research

Save this analysis and keep the funds you follow together in My Desk.

Sign in to save articles or follow funds.
More from Private Infrastructure Daily
Digital Infra

Digital Realty eyes 1GW data center campus in Kokomo, Indiana

The plan covers three single-story data centers across roughly 3 million sq ft and a possible full buildout by 2033, according to Data Center Dynamics.
Digital Infra

Odisha cabinet approves $18.62m disaster recovery data center in Keonjhar

The Keonjhar site would back up the state's primary data center in Bhubaneswar, with more than $17m covered by a Fifth State Finance Commission grant.
The Wrap

AEP to buy up to 1.6 GW Mainspring units, plans $4B Cheyenne fuel cells

The eight-year Mainspring agreement carries a stated ceiling of up to $4 billion; the 702 MW Cheyenne project pairs Bloom Energy fuel cells with a 20-year Google PPA.
Elsewhere in the networkAll titles →
Every weekday · 6:30 a.m. ET

The Morning Brief

The latest from Private Infrastructure Daily, in your inbox every weekday. Free.