Hillwood Polska shrinks buildings at planned Warsaw-area 130MW data center campus after opposition

The Reguły campus southwest of Warsaw will sit further from homes behind a landscaped buffer, after residents raised water, power and noise concerns.

At a glance

10-second brief
  • Hillwood Polska has redrawn the layout of its planned 130MW data center campus at Reguły, southwest of Warsaw.

  • TVP3 Warsaw reported residents' concerns over water and electricity consumption and local noise, according to DCD.

Hillwood Polska has redrawn the layout of its planned 130MW data center campus at Reguły, southwest of Warsaw. Buildings will be smaller and sit further from homes after residents objected to the project, Data Center Dynamics reported on 19 October.

"The changes significantly increase the investment's distance from residential development," Ilona Śmigasiewicz, Hillwood Polska's data center development director, said in a statement cited by DCD. She said a landscaped green buffer would provide additional separation and that residents' opinions had been an important element of the project's development.

The campus occupies a 54-acre plot in Michałowice commune between the Warsaw commuter rail line and an arterial road into the city. Announced in December 2025, the plan calls for four separate buildings constructed in phases, supporting cloud computing, IT systems, internet services and other corporate digital solutions. The redesign comes about ten months after the announcement, before any of the buildings have gone up.

TVP3 Warsaw reported residents' concerns over water and electricity consumption and local noise, according to DCD. Some residents described the planning process as opaque. In August 2026, residents of the Warsaw suburb of Józefosław criticised a proposed data center in the nearby Piaseczno district, saying it would worsen water pressure problems there.

Hillwood Polska is the Polish arm of the US developer Hillwood and owns and manages 22.6 million sq ft (2.1 million sqm) of warehouse space in Poland.

Continue your research

Save this analysis and keep the funds you follow together in My Desk.

Sign in to save articles or follow funds.
Sources & further reading
Data Center Dynamics · TVP3 Warsaw (via DCD)
More from Private Infrastructure Daily
Digital Infra

Israel's Electricity Authority caps new data center connection capacity at 200MW, with per-megawatt guarantees

The reported rules follow a queue of about 27GW of projects and require NIS 2 million ($643,300) in guarantees per megawatt requested.
Digital Infra

Alcoa to sell Massena smelter site to data center developer for up to $315m

Alcoa expects $50m to $65m at closing, with up to $250m more as the buyer's capacity is approved and commissioned.
The Wrap

Microsoft-NiSource power deal makes data center customer fund its own generation

The 20-year contract, closed Oct. 19, adds roughly 1.1GW to NiSource's portfolio from 2028 and covers a northern Indiana data center.