Stack Infrastructure affiliate files for second Lancaster data center building
The DFW02B filing carries a $540 million construction budget and a March 2027 to December 2028 schedule.
At a glance
Stack Infrastructure's affiliate SI DFW02CAMPUS LLC filed this month for DFW02B, a 350,045 sq ft data center and office building in Lancaster, Data Center Dynamics reported.
The Texas Department of Licensing and Regulation application sets a $540 million construction budget and a March 2027 to December 2028 schedule.
The $540 million budget and 54MW figure work out to roughly $10 million per megawatt, if they cover the same scope.
Stack Infrastructure's affiliate SI DFW02CAMPUS LLC filed this month for DFW02B, a 350,045 sq ft data center and office building in Lancaster, Data Center Dynamics reported. The two-story building would sit at 1130 E. Belt Line Road in Dallas County.
The Texas Department of Licensing and Regulation application sets a $540 million construction budget and a March 2027 to December 2028 schedule. Stack's sales brochure assigns 54MW to the building and describes DFW02 as a 500MW campus on 193 acres in South Dallas that could reach five buildings, 1.76 million sq ft and an on-site substation.
Stack's latest filing follows DFW02A at 1000 E Belt Line Road, a 360,030 sq ft, two-story building due for completion in March 2027. DFW02A was filed in January 2025, with follow-up works running to March 2028. DFW02B's construction start therefore lands in the same month DFW02A is scheduled to finish, per those filings.
The $540 million budget and 54MW figure work out to roughly $10 million per megawatt, if they cover the same scope. The filing does not break the budget down that way, and it is a per-building figure, not a campus one, because the other four buildings have no disclosed cost.
| Building | Address | Size | Power | Construction window |
|---|---|---|---|---|
| DFW02A | 1000 E Belt Line Road, Lancaster | 360,030 sq ft | Not disclosed | Completion March 2027; follow-up works to March 2028 |
| DFW02B | 1130 E Belt Line Road, Lancaster | 350,045 sq ft | 54MW (brochure) | March 2027 to December 2028; $540 million |