PowerHouse, Big Watt win Taylor, Texas approval for 1GW gas-backed campus

The 664-acre Williamson County project pairs a 750MW on-site plant with a first phase targeting 500MW and first power in the first half of 2028.

At a glance

20-second brief
  • PowerHouse and Big Watt Digital secured unanimous Taylor, Texas City Council approval last week for a 664-acre data center campus designed for up to 1GW, backed by a new 750MW on-site natural gas plant.

  • First power is targeted for the first half of 2028, with the first phase aiming to offer 500MW.

  • The campus is a bet on the shift toward self-supply as much as on tenant demand.

PowerHouse and Big Watt Digital secured unanimous Taylor, Texas City Council approval last week for a 664-acre data center campus designed for up to 1GW, backed by a new 750MW on-site natural gas plant. The site, previously known as Project Mustang, was reported by Data Center Dynamics.

First power is targeted for the first half of 2028, with the first phase aiming to offer 500MW. The site sits in Williamson County between FM 112 and US 79, roughly 35 miles northeast of Austin, and will use a closed-loop cooling system to reduce water use.

The campus is a bet on the shift toward self-supply as much as on tenant demand. Alex Hern, Big Watt Digital’s co-CEO and co-founder, said pairing digital infrastructure with dedicated, behind-the-meter power addresses “access to reliable power” without relying solely on incremental grid capacity.

The reporting does not specify how the 1GW campus would be supplied beyond the 750MW plant; phase one's 500MW is the only load level tied to a delivery date. That leaves the premium on firm, dispatchable generation as an open question for the remaining capacity.

Taylor campus targets 1,000MW; its on-site gas plant supplies 750MW
Capacity in MW. Phase one of 500MW is the only load tied to a delivery date.
Campus dOn-site Phase on
DATA CENTER DYNAMICS
Continue your research

Save this analysis and keep the funds you follow together in My Desk.

Sign in to save articles or follow funds.
Sources & further reading
Data Center Dynamics
More from Private Infrastructure Daily
Digital Infra

CtrlS signs non-binding LOI for 150MW Bihar data center

The $1 billion letter of intent covers a Bodh Gaya hyperscale campus; CtrlS's Rs 400 crore Patna facility is live with 12MW of IT capacity.
Digital Infra

Virginia senator Russet Perry proposes three-year data center moratorium

Senate Bill 843 would stop state agencies from approving data center planning applications for three years from July 1, 2027.
Capital

Ares and Astatine file SEC registrations for three pooled infrastructure vehicles

The vehicles list an undisclosed offering amount and $0 sold to date; SWI raised €800 million for data-center buildouts.
Elsewhere in the networkAll titles →
Every weekday · 6:30 a.m. ET

The Morning Brief

The latest from Private Infrastructure Daily, in your inbox every weekday. Free.