PJM approves 2.1 GW of Engie storage and LS Power gas uprate

PJM expects the approved projects online by mid-2029; the expedited track that cleared them expires at the end of 2027.

At a glance

20-second brief
  • PJM Interconnection has approved the initial three projects in its Expedited Interconnection Track, clearing a combined 2.1 GW.

  • Engie IR Holdings plans an 860-MW storage project in Crawford, Pennsylvania, and an 800-MW storage project in Morrow, Ohio, while LS Power plans a 455-MW uprate at its Hunterstown combined cycle plant.

  • The approvals land against tight supply in PJM, where data centers are pushing demand forecasts higher.

PJM Interconnection has approved the initial three projects in its Expedited Interconnection Track, clearing a combined 2.1 GW. Utility Dive first reported the approvals, and PJM expects the projects online by mid-2029.

Engie IR Holdings plans an 860-MW storage project in Crawford, Pennsylvania, and an 800-MW storage project in Morrow, Ohio, while LS Power plans a 455-MW uprate at its Hunterstown combined cycle plant. PJM disclosed the projects; LS Power bought the Hunterstown plant from Platinum Equity in 2024.

FERC approved the expedited track in June, and PJM opened the application window on July 31. Eligible projects must exceed 250 MW, carry backing from a primary siting authority and be able to begin operating within three years. PJM will consider up to 10 requests a year, and the process expires at the end of 2027 — roughly 18 months before the approved projects are due online.

The approvals land against tight supply in PJM, where data centers are pushing demand forecasts higher. PJM links the combination to sharply higher capacity costs and rising utility bills in some areas. PJM's other efforts include a pending reliability backstop procurement and updates to its surplus interconnection service rules that could let new generation use existing interconnection capacity.

PJM expedited track: 1,660 MW of storage, 455 MW of gas
Capacity of the three projects cleared in the first round
Engie — Crawford, Pa. (storage)860 MW
Engie — Morrow, Ohio (storage)800 MW
LS Power — Hunterstown uprate, Pa. (gas)455 MW
PJM INTERCONNECTION, VIA UTILITY DIVE
Continue your research

Save this analysis and keep the funds you follow together in My Desk.

Sign in to save articles or follow funds.
Sources & further reading
Utility Dive
More from Private Infrastructure Daily
Energy Transition

Four-hour storage undercuts gas peakers on cost in global markets, Wood Mackenzie says

In the US, four-hour storage for a 2026 commercial operation date is 65% to 75% cheaper than new open-cycle gas peakers, depending on whether state-level carbon pricing applies.
Energy Transition

Renew Home rebrands as Everyday Electric, launches whole-home virtual power plant

CEO Ben Brown says the VPP can reduce the need for new centralized generation and lower costs for all ratepayers; expected capacity and payments were not disclosed.
The Wrap

Bain projects $5tn to $6.5tn data center spending through 2030

Power availability, electrical labor and local opposition are the near-term constraints, not capital.
Elsewhere in the networkAll titles →
Every weekday · 6:30 a.m. ET

The Morning Brief

The latest from Private Infrastructure Daily, in your inbox every weekday. Free.