A Daily Network publication
Explore the network
Private Infrastructure Daily
Independent Intelligence on Infrastructure Capital
Tuesday, September 29, 2026The Morning Brief →Sign in
Energy Transition

New York awards 950 MW of batteries in first bulk storage round

NYSERDA says the first bulk storage round more than doubles all utility-scale storage awarded, contracted and installed in the state, and payments begin only once projects run.

New York's first bulk energy storage procurement awarded 950 MW of lithium batteries, while its 2025 Tier 1 Renewable Energy Standard solicitation selected 700 MW of solar, wind and hydroelectric generation; NYSERDA expects the two rounds to support 1,000 jobs and draw more than $3.7 billion in private investment.

The storage figure lands against a target Albany doubled in 2022, to 6 GW online by 2030, and against how little of it is built. NYSERDA said the selected projects more than double all the utility-scale energy storage awarded, contracted and installed in New York to date, which leaves the state's entire cumulative base, after this round, still smaller than what the round itself selected.

The awards also arrived in a year when New York pushed back its emissions targets, though officials say the state remains committed to clean energy and has not adjusted its procurement goals, and the 70% renewable-by-2030 target set when the CLCPA passed in 2019 is unchanged. NYSERDA President and CEO Doreen Harris called the projects part of New York's all-of-the-above energy strategy, and Rai of AEU said they mean more homegrown power, more flexibility for the grid and more investment in communities. The state has moved its emissions dates without moving the volume it solicits.

The state has moved its emissions dates without moving the volume it solicits.

An eight-hour asset in Chautauqua County

Three storage projects were named: Key Capture Energy is developing a four-hour, 94-MW facility in Ulster County and a 150-MW project in Suffolk County, and the eight-hour, 140-MW Lighthouse Energy Storage project in Chautauqua County is proposed by Grid Connected Infrastructure LLC and Neoen US.

The capacity band across the named projects is tight, from 94 MW to 150 MW, but the duration band is not: it runs four hours to eight, and the coverage does not say how New York intends to dispatch any of the three. An eight-hour battery discharges for twice as long as the four-hour projects beside it, so if the next round skews longer, that suggests the state is buying something closer to firm capacity; if it repeats the four-hour majority, the opposite.

Payments to the contracted projects begin only once they are operational, putting construction and completion risk on the developers until the assets run. That is the term that matters on a round NYSERDA sizes at more than $3.7 billion of private capital: the state's payments start at operation, not at award. The report gives neither contract prices nor Tier 1 terms, so the generation and batteries cannot be compared on revenue.

The buyer a merchant market will not supply

State procurement has been carrying more of the load in Albany as the mandates have come under pressure: progress toward the state's 2040 fossil-free grid has been scant, and New York lost its largest carbon-free generator when Indian Point closed, leaving a nuclear push that is that gap made visible. What the storage and Tier 1 rounds add is different in kind, because on a project that takes years to permit and build, a state contract is the buyer a merchant market will not supply on its own, and New York is now buying on a published schedule.

The state's renewables procurement has been where the sharper fights sit: offshore wind's real fight is now over who signs the offtake, with the politics running through Albany and Sacramento rather than the turbine supply chain. A Tier 1 solicitation draws less of that attention, but it rests on the same condition, a state willing to sign as counterparty.

The round also splits the transition trade in two: the batteries sit inside a program with a 6 GW goal and a procurement calendar attached, while the solar, wind and hydro arrived through the Tier 1 solicitation, whose pricing the coverage does not include. Contracted dispatchable power that can sell electrons today prices differently from renewable platforms still looking for a buyer, and folding both halves into one announcement makes the distinction easy to miss.

Grid access is the asset this round does not supply, because a signed award is a contract, not a connection, and generation has become a derivative of permission. The payment trigger is where that shows up in the numbers: developers carry a project from award to energization on their own balance sheets, and the state's obligation begins only at the far end of it.

NYSERDA plans to issue a second annual bulk energy storage request for proposals by the end of this year; measured against its 3 GW three-solicitation intention and the 950 MW selected here, the two remaining rounds carry roughly 2 GW, twice round one's volume. Whether the second request repeats the four-to-eight-hour spread or leans longer is the next thing the state's numbers will show.

950 MW selected against a 3 GW program and a 6 GW target
2030 stoFirst thRound 1
NYSERDA, FIRST THREE ENERGY STORAGE SOLICITATIONS
ProjectDeveloperCapacity / durationStatus
Ulster County storageKey Capture Energy94 MW / 4-hourSelected
Suffolk County storageKey Capture Energy150 MW / 4-hourSelected
Lighthouse Energy Storage, Chautauqua CountyGrid Connected Infrastructure LLC and Neoen US140 MW / 8-hourProposed
Continue your research

Save this analysis and keep the funds you follow together in My Desk.

Sign in to save articles or follow funds.
More from Private Infrastructure Daily
The Wrap

Washington's grid money stops buying new corridors

The $1.9 billion SPARK package buys 23 gigawatts on lines that already exist, turning the data center buildout's power schedule into a question of tariff design.
Elsewhere in the networkAll titles →
Every weekday · 6:30 a.m. ET

The Morning Brief

The latest from Private Infrastructure Daily, in your inbox every weekday. Free.