Halmar completes Yankee Stadium station on $965M MTA subway program
Remaining 12 stations are expected to finish in early 2027, according to a company statement.
At a glance
Halmar has finished work at the Yankee Stadium subway station under a $965 million MTA program that uses a design-build-finance-maintain concession, Construction Dive reported.
Construction at the remaining 12 stations is expected to finish in early 2027, according to a company statement sent to Construction Dive.
The program covers replacement stations at five locations and new vertical circulation infrastructure at eight, according to the statement.
Halmar has finished work at the Yankee Stadium subway station under a $965 million MTA program that uses a design-build-finance-maintain concession, Construction Dive reported.
Construction at the remaining 12 stations is expected to finish in early 2027, according to a company statement sent to Construction Dive.
The program covers replacement stations at five locations and new vertical circulation infrastructure at eight, according to the statement. All new vertical transportation systems at the Yankee Stadium station are operational.
| Role | Party |
|---|---|
| Developer and financial sponsor | Halmar Infrastructure Development |
| Concessionaire holding prime contract | Elevated Accessibility Enhancements |
| Construction lead | Halmar International |
| Civil work | Forte Construction |